Power Platform Governance Roadmap
All epics
S3P2DraftFuture Proof
Governance Zones & Environment Strategy
Ensure every solution runs inside boundaries proportionate to its business impact, with a coherent environment strategy replacing today's ad-hoc estate.
Implementation of the Green / Amber / Red / Black zone model, managed environments, environment groups and naming standards.
Lead
Marius Oprea
Owner
—
Deliverables
7
Effort
14.5
sprints
Delivered
0/7
Deliverables
| Ref | Title | Phase | Priority | Owner | Sprints | Status | |
|---|---|---|---|---|---|---|---|
| S3.1 | Confirm the four-zone model and classification criteria Agree Green, Amber, Red and Black as the governance zones, with the business impact and risk assessment criteria that place a solution in each, and the project types that map to them. | Phase 1 | P1 | Marius Oprea | 1 | Draft | |
| S3.2 | Roll out managed environments per zone Apply managed environments to the Red and Black zones first, then Amber, taking the sharing limits, enforced policies and security features that come with them. | Phase 2 | P1 | Marius Oprea | 3 | Draft | |
| S3.3 | Establish environment groups and rules Create environment groups per zone with the associated rules. None exist today. | Phase 2 | P1 | Dogaru Eduard | 2 | Draft | |
| S3.4 | Configure environment routing to personal developer environments Route makers into their own personal development environments rather than the default environment, using the welcome message to set expectations. | Phase 2 | P2 | Ovidiu Kislaposi | 1.5 | Draft | |
| S3.5 | Define shared regional production environments per OpCo Establish the Red zone shared production environments that structurally used and properly supported solutions migrate into, owned by the regional teams. | Phase 2 | P2 | Vamsi Namuduri | 2 | Draft | |
| S3.6 | Environment request and provisioning process A standard route to request an environment, including approval, naming, access group provisioning and registration of the responsible owner. | Phase 2 | P2 | Ovidiu Kislaposi | 2 | Draft | |
| S3.7 | Zone migration path for existing solutions Define and run the route that moves existing solutions out of personal productivity into the zone that matches their actual business impact. | Phase 3 | P3 | ACE Solutioning | 3 | Draft |
By phase
- Phase 11 · 1 spr
- Phase 25 · 10.5 spr
- Phase 31 · 3 spr
By priority
- P13 items
- P23 items
- P31 items