Power Platform Governance Roadmap

All epics
S6P1In ProgressPlatform Run the Business

Support & Service Model

Replace best-effort, admin-dependent support with a structured service that has named owners, defined tiers and published SLAs.

SLA-backed application support, the service request catalogue, tier model and OpCo routing.

Lead
John Fernando
Owner
—
Planned
—
Deliverables
7
Effort
19.5
sprints
Delivered
2/7

Deliverables

RefTitlePhasePlannedPriorityOwnerSprintsStatus
S6.1
Power Platform service request catalogue in ServiceNow
Define and publish the request catalogue entries with their field definitions, covering environment requests, DLP changes, licence assignment and access.
Phase 1Q1 2027P1John Fernando3In Progress
S6.2
Standard operating procedures per request type
The steps and required fields for each request type, written so first line can execute them without escalation.
Phase 1—P1Marius Oprea3Delivered
S6.3
Support tier model and OpCo routing
Decide which items route to which OpCo and where L3 sits. This is a tier ownership decision, not a flow design task, and it blocks several downstream items.
Phase 1Q1 2027P1John Fernando4In Progress
S6.4
SLA definitions aligned to business criticality
Publish the SLA offering, with response and recovery targets that align to the RTO requirements of each business criticality level.
Phase 2—P2Vamsi Namuduri2Draft
S6.5
Solution handover and BAU acceptance gate
No solution enters BAU without an SoP handed to first and second line and a named third line individual. Define the gate and its acceptance criteria.
Phase 2—P1Ovidiu Kislaposi2In Progress
S6.6
Knowledge transfer and support documentation
Run the handover sessions and publish the known-error and how-to content that first line needs.
Phase 2—P2John Fernando1.5Delivered
S6.7
Self-service portal for platform requests
A central place where business users and stakeholders trigger a structured process for environments, DLP changes, licences and access.
Phase 3—P2Ovidiu Kislaposi4Draft

By phase

  • Phase 13 · 10 spr
  • Phase 23 · 5.5 spr
  • Phase 31 · 4 spr

By priority

  • P14 items
  • P23 items
  • P30 items